Projects
Sheet Pile Monitoring, A16 Rotterdam, NL
Rotterdam, The Netherlands
Project duration: 2022 – 2024
During the construction of the new A16 Rotterdam motorway, Basetime monitored the sheet pile wall along the River Rotte. This structure formed part of the activities executed by the “Groene Boog” alliance. Locator One units were used to continuously track horizontal deformation, ensuring structural stability throughout the construction process.
A demonstrably safer working environment through continuous sheet-pile monitoring, significantly reducing risks for workers and liability toward the client and stakeholders.
Project Purpose
The objective was to precisely track horizontal displacement of the sheet pile wall, as significant vertical settlement was not expected. The monitoring setup had to detect deviations at an early stage, supporting safe and controlled execution of the infrastructure works.
Implemented Solution
Metal mounting plates were installed on the top of the sheet pile wall, each carrying a Locator One unit. These devices automatically collected measurements according to a fixed regime. Configured alert and limit values enabled immediate signaling of anomalies.